Electricity restored to Northeastern states

Mbah said that the connection of the new substation to the national grid had enhanced power reliability, diversified transmission routes, and improved emergency response capabilities in the North Eastern region.

Published

on

The Transmission Company of Nigeria (TCN)says it has successfully restored normal bulk electricity supply to the Northeastern part of the country.

Mrs Ndidi Mbah, TCN General Manager, Public Affairs, in a statement in Abuja on Sunday, said that the supply was restored through the 330kV and 132kV Jos-Bauchi-Gombe transmission lines.

Mbah said that the lines were initially switched off to enable TCN energise the new Bauchi Substation – one of the biggest substations in the region to the national grid.

Advertisement

”The transmission lines have now been reconnected back to the grid. Consequently, supply to the northeast has been restored since the June 19 at about 4.45 pm.

”With the project completed, bulk power transmission has been restored to Jos and Yola Electricity Distribution Companies, which supply electricity to customers in Bauchi, Gombe, Yobe, Damaturu, Adamawa, and Taraba states ,”she said.

Mbah said that the connection of the new substation to the national grid had enhanced power reliability, diversified transmission routes, and improved emergency response capabilities in the North Eastern region.

Advertisement

According to her, TCN appreciate the patience and support of the affected customers during the outage.

Opinion Nigeria is a practical online community where both local and international authors through their opinion pieces, address today’s topical issues. In Opinion Nigeria, we believe in the right to freedom of opinion and expression. We believe that people should be free to express their opinion without interference from anyone especially the government.